ERP Project Rollout
at a Large Optical Maker
Project Background
Provision of Project Management for ERP rollout through all phases to the successful go-live.
End system is a complex multiple-site situation - Japan HQ, Order Center, 3PL Distribution Center connecting back to US data center - which involved multiple layers of IT and functional expertise, and multi-lingual / multi-culture savvy to implement.
Parameter | Value |
---|---|
Team Members | PM x 1, Consultant x 6, Developer x 4, Engineer x 2, Functional Key User x 6 |
Users | 100 |
Project Duration (Months) | 24 months |
Project Effort (Months) | 400 person-months |
Sites | Tokyo, NY, CA |
Problems
- High inventory levels
- Inefficient distribution logistics
- Non-standard functional processes combined with poor human interface between Japan and US
- SOX liabilities when considering legacy system
- Poor supply chain management with existing system
- Reports inflexible, opaque or unavailable
- Legacy AS/400 system code opaque, undocumented and ill-designed
Solution
- Implement corporate standard Baan ERP
- Adopt corporate standards and practices
- Implement a mentor-centric “Buddy System” to assist new users in learning global processes and practices
- Move 3PL for higher efficiency in distribution
Benefits
- Large efficiency gain in inventory levels due to ERP and new 3PL
- Transparency in reporting
- Standard, secure, SOX compliant processes
- Improved communications between Japan and US
- System flexibility and scalability
Technology
- Baan ERP
- Unisys Hardware running Windows Server for Datacenter
- Microsoft SQL Server
- Business Objects and Crystal Reports
- EDI via TIE and Argo21